Moral Hazard, Incentive Contracts and Risk: Evidence from Procurement / Gregory Lewis, Patrick Bajari.

NBER Working papers Available online

View online
Format:
Book
Author/Creator:
Lewis, Gregory.
Contributor:
National Bureau of Economic Research.
Bajari, Patrick.
Series:
Working Paper Series (National Bureau of Economic Research) no. w17647.
NBER working paper series no. w17647
Language:
English
Physical Description:
1 online resource: illustrations (black and white);
Place of Publication:
Cambridge, Mass. National Bureau of Economic Research 2011.
Summary:
Deadlines and penalties are widely used to incentivize effort. We model how these incentive contracts affect the work rate and time taken in a procurement setting, characterizing the efficient contract design. Using new micro-level data on Minnesota highway construction contracts that includes day-by-day information on work plans, hours actually worked and delays, we find evidence of moral hazard. As an application, we build an econometric model that endogenizes the work rate, and simulate how different incentive structures affect outcomes and the variance of contractor payments. Accounting for the traffic delays caused by construction, switching to a more efficient design would substantially increase welfare without substantially increasing the risk borne by contractors.
Notes:
Print version record
December 2011.

The Penn Libraries is committed to describing library materials using current, accurate, and responsible language. If you discover outdated or inaccurate language, please fill out this feedback form to report it and suggest alternative language.

Find

Home Release notes

My Account

Shelf Request an item Bookmarks Fines and fees Settings

Guides

Using the Find catalog Using Articles+ Using your account