1 option
Electric utility resource planning : economics, reliability, and decision-making / Steven Sim.
- Format:
- Book
- Author/Creator:
- Sim, Steven, 1982- author.
- Language:
- English
- Subjects (All):
- Electric power production.
- Electric power distribution.
- Electric utilities.
- Physical Description:
- 1 online resource (430 pages)
- Edition:
- Second edition.
- Place of Publication:
- Boca Raton, FL : CRC Press, Taylor & Francis Group, LLC, [2024]
- Summary:
- With this 2nd edition, author Dr. Steven Sim again applies the experience and insights he gained from more than 30 years of resource planning for Florida Power & Light (FPL). As one of the largest electric utilities in the U.S., FPL has faced a multitude of resource planning challenges, including how to get to zero carbon.
- Contents:
- Cover
- Half Title
- Title Page
- Copyright Page
- Contents
- Acknowledgments
- Author
- Part I: The Fundamentals of Electric Utility Resource Planning
- Chapter 1: Introduction
- Why Write this Book?
- Who is this Book Written For?
- An Overview of the Book's First Edition (i.e., Part I of this Book)
- An Overview of the Book's Second Edition (i.e., Part II of this Book)
- Are We Keeping it Simple?
- A Few Words Regarding Assumptions Used in the Book
- A Couple of Disclaimers
- Chapter 2: How Does an Electric Utility Actually "Work"?
- Two "Types" of Electric Utilities
- Whose Perspective Will Be Taken?
- What Aspects of an Electric Utility Will we Focus on?
- Types of Generating Units a Utility May Have
- How Does a Utility Decide which Generating Units to Use?
- Let's Create a Hypothetical Utility System
- Now Let's Operate our Hypothetical Utility System
- Utility System Operation on the Summer Peak Day
- Utility System Operation Over the Course of a Year
- So What Have We Learned and Where Do We Go Next?
- Chapter 3: Overview of Utility Resource Planning
- One More Assumption Regarding Our Hypothetical Utility System
- Three Questions Utility Resource Planning Must Always Answer
- Reliability Analysis: When Does a Utility Need to Add New Resources and What is the Magnitude of Those Needed Resources?
- Reserve Margin Perspective (Simple to Calculate)
- Probabilistic Perspective (Not so Simple to Calculate)
- Which Reliability Perspective is More Important?
- Resource Option Evaluation and Selection: What is the Best Resource Option to Select for a Given Utility?
- Two Basic Types of Resource Options: Supply and Demand Side Management Options
- Integrated Resource Planning (IRP)
- Economic Evaluations
- Preliminary Economic Screening Evaluation of Supply Options.
- Preliminary Economic Screening Evaluation of DSM Options
- Final (or System) Economic Evaluations
- Non-Economic Evaluations
- Non-Economic Consideration Example (I): The Length of Time it Takes Before a Resource Plan Becomes the Economic Choice
- Non-Economic Consideration Example (II): The Utility System's Fuel Usage due to a Resource Plan
- Non-Economic Consideration Example (III): The Utility System's Air Emissions due to a Resource Plan
- Chapter 4: Reliability Analyses for Our Utility System
- When Does Our Utility System Need New Resources?
- What is the Magnitude of the New Resources Needed by Our Utility System?
- What have We Learned and What is Next?
- Chapter 5: Resource Option Analyses for Our Utility System: Supply Options
- Types of Supply Options Under Consideration
- Capital Costs: Rows (1) Through (3)
- Other Fixed Costs: Rows (4) Through (7)
- Operating Costs: Rows (8) Through (16)
- Preliminary Economic Screening Evaluation of the Supply Options
- Creating the Competing "Supply Only" Resource Plans
- Final (or System) Economic Evaluation of Supply Options
- Overview
- Total Cost Perspective (CPVRR) for the Supply only Resource Plans
- Electric Rate Perspective (Levelized System Average Electric Rate) for the Supply only Resource Plans
- Chapter 6: Resource Option Analyses for Our Utility System: DSM Options
- Types of DSM Resource Options Under Consideration
- Preliminary Economic Screening Evaluation of DSM Options: Understanding the Cost-Effectiveness Screening Tests
- Preliminary Economic Screening Analyses of DSM Options: Results
- Creating the Competing "With DSM" Resource Plans
- Final (or System) Economic Analysis of DSM Options
- Results for the with DSM Resource Plan 1
- Results for the with DSM Resource Plan 2
- Chapter 7: Final Resource Option Analyses for Our Utility System.
- Economic Comparison of the Resource Plans
- Non-Economic Analyses of the Resource Plans
- "Cross-Over" Time to Being the Most Economic Resource Plan
- System Fuel Use
- System Air Emissions
- Summary of Results from the Resource Option Analyses for Our Utility System
- Chapter 8: Are We Done Yet? Other Factors that Can (and Will) Complicate Resource Planning Analyses
- Constraints on Solutions: Six Examples
- Examples of "Absolute" Constraints
- Siting/Geographic Constraints
- Potential Tightening of Environmental Regulations
- Examples of Legislative/Regulatory-Imposed Constraints
- "Standards" / (Quotas) for Specific Types of Resource Options
- Prohibition of Specific Resource Options
- Examples of Utility-Imposed Constraints
- System Reliability Constraints
- The Voluntary Nature of DSM Options
- Load Shape Constraint
- What are the Impacts of Addressing these Constraints?
- Part II: Moving toward Zero Carbon
- Chapter 9: An Overview of Part II
- Introduction
- A Different Approach is Taken in Part II
- How Part II is Structured
- Chapter 10: Moving toward Zero Carbon: How Many MW of New Resources Will be Needed?
- The First Estimation Approach
- The Second Estimation Approach
- How Accurate do We Believe the Second Estimation Approach Is?
- A "What If" Analysis: How Many Additional New Resource MW Would be Needed if Our Utility's Nuclear Capability Was Not Available?
- Summary: Key Takeaways Regarding the Magnitude of New Resource MW Needed to Reach a Zero-Carbon Goal
- Chapter 11: Moving toward Zero Carbon: Resource Planning Considerations for Solar (PV) Resources
- Solar Installed Costs (/kW): 2009-2022
- Tax Credits for PV from the 2022 Inflation Reduction Act (IRA)
- Impacts of PTC Over the 25-Year Analysis Period.
- What Do We Conclude from this Discussion of the 2022 IRA's PTC Impact on Solar Resource Options?
- A More Complete Look at the Firm Capacity Value Aspect of Solar
- Firm Capacity Value of PV at Our Utility's Winter Peak Hour
- Summer Firm Capacity Values as Increasing Amounts of PV are Added in the Future
- How Serious are the Challenges that Utility Resource Planners will Face from These Two PV Firm Capacity Value Characteristics?
- System Reliability Analysis During the Transition Period
- Summary: Key Takeaways for Resource Planning Regarding PV Resources
- Chapter 12: Moving toward Zero Carbon: Resource Planning Considerations for Battery Storage Resources
- A Representative Projection of Battery Storage Installed Costs ( Per kW): 2023-2030
- Tax Credits from the 2022 Inflation Reduction Act (IRA)
- A Graphical Look at the Firm Capacity Value Aspect of Battery Storage
- A Better Method to Determine the Needed Duration of Battery Storage Options
- The Relationship between the Needed Duration of Battery Storage Options and the Cost of Batteries
- A Brief Look at Battery-and-PV Combinations in Regard to System Reliability
- Summary: Key Takeaways for Resource Planning Regarding Battery Storage Resources
- Chapter 13: Moving to Zero Carbon: Ramifications for System Operations and Transmission Planning
- Solar Curtailment
- Operation of Existing Conventional Generation with Ever-Increasing Amounts of PV
- Inverter-Based Resources (IBRs) and System Stability
- Summary: Key Takeaways Regarding System Operations, Transmission Planning, and Resource Planning
- Chapter 14: Final Thoughts (Including Some Opinions)
- A Quick Look Back
- Summary of the Key Points We Have Learned about Utility Systems in General
- Summary of the Key Lessons We Have Learned Regarding Utility Resource Planning.
- Summary of the Key Lessons We Have Learned Regarding Moving Toward Zero Carbon
- A Few Opinions on Various Topics
- What Lies ahead for Electric Utilities and Utility Resource Planning?
- Closing Thoughts
- Appendix A: Fundamental Principles of Electric Utility Resource Planning
- Appendix B: Glossary of Terms
- Appendix C: Mini-Lesson #1: Concepts of Revenue Requirements, Present Valuing of Costs and Discount Rates, Cumulative Present Value of Revenue Requirements, and Levelized Costs
- Appendix D: Mini-Lesson #2: Further Discussion of the Limitations of a Screening Curve Analytic Approach
- Appendix E: Mini-Lesson #3: Further Discussion of the RIM and TRC Preliminary Cost-Effectiveness Screening Tests for DSM
- Appendix F: Mini-Lesson #4: How Can a Resource Option Result in Lower Costs but Increase Electric Rates?
- Appendix G: Mini-Lesson #5: How Can a Resource Option That Produces Emissions Result in Low Utility Total System Emissions? ("The Taxi Cab Example")
- Index.
- Notes:
- Includes index.
- Description based on print version record.
- Description based on publisher supplied metadata and other sources.
- Other Format:
- Print version: Sim, Steven Electric Utility Resource Planning
- ISBN:
- 1-000-95953-8
- OCLC:
- 1410916665
The Penn Libraries is committed to describing library materials using current, accurate, and responsible language. If you discover outdated or inaccurate language, please fill out this feedback form to report it and suggest alternative language.