1 option
Programme management in construction / Peter T. Barnes, Roy Farren, Ali D. Haidar and Kenneth P. Wells.
- Format:
- Book
- Author/Creator:
- Barnes, Peter, 1954- author.
- Farren, Roy, author.
- Haidar, Ali D., author.
- Wells, Kenneth P., author.
- Language:
- English
- Subjects (All):
- Project management.
- Construction industry--Management.
- Construction industry.
- Physical Description:
- 1 online resource (156 pages)
- Place of Publication:
- London : ICE Publishing, 2015.
- Summary:
- 'Programme Management in Construction' provides a comprehensive introduction to the application of programme management in the construction industry, demonstrating detailed coverage of programme management techniques through best practice guidance and case study examples.
- Contents:
- T309-00.pdf
- T309-01.pdf
- 1.1. An overview
- 1.2. Programme management definitions
- Figure 1.1
- Figure 1.2
- 1.3. Programme phases
- Figure 1.3
- Figure 1.4
- 1.3.1 Pre-construction
- 1.3.2 Construction
- 1.3.3 Post-construction
- 1.3.4 Facility management
- 1.4. The role of the programme manager
- Figure 1.5
- Figure 1.6
- Figure 1.7
- References
- Brown JT (2008)
- Martinsuo M and Lehtonen P (2006)
- Project Management Institute (2008)
- Ritz G and Levy S (2013)
- Tobis I and Tobis M (2002)
- T309-02.pdf
- 2.1. Programme process
- Figure 2.1
- Figure 2.2
- 2.2. Programme requirements
- Figure 2.3
- 2.3. Scope management
- 2.4. Cost management
- Figure 2.4
- Figure 2.5
- 2.5. Schedule management
- 2.6. Programme delivery methods
- 2.7. Programme management plan
- 2.8. Design stage management of a programme
- 2.9. Delivering and measuring programme quality
- 2.10. Programme cost stage management
- 2.11. Building information modelling (BIM)
- 2.12. Quality control
- 2.13. Programme commissioning
- 2.14. Programme management report
- 2.15. Programme management quality assurance
- 2.16. Programme management consultancies' scope of services - a™case study
- 2.16.1 Case study (consultant's role)
- 2.16.2 Organisation strengths and resources
- 2.16.3 Preparation of detailed design and tender documents
- Figure 2.6
- 2.16.4 Programme supervision
- Figure 2.7
- Figure 2.8
- 2.16.5 Contractual issues
- 2.16.6 Quality control and quality control services
- Table 2.1
- 2.17. Design and design activities
- 2.18. Programme pre-construction documents
- Figure 2.9
- 2.19. Programme execution
- 2.19.1 Human resources
- 2.19.2 Supervision and engineering
- 2.19.3 Technical support
- 2.20. Programme management compared to portfolio management
- 2.21. Summary: objectives of programme management.
- Figure 2.10
- Dietrich, PH and Lehtonen, P (2005)
- Eweje J, Turner R and Müller R (2012)
- Pellegrinelli S (2008)
- Reiss G and Rayner P (2012)
- Teller J et al. (2012)
- T309-03.pdf
- 3.1. Pre-planning framework in programme management
- 3.2. Pre-goal-setting
- Figure 3.1
- 3.3. Execution modelling
- Figure 3.2
- Figure 3.3
- 3.4. Decision makers' hierarchy in a programme
- Figure 3.4
- Figure 3.5
- 3.4.1 Programme management team responsibilities during pre-planning
- 3.5. Decision-making framework
- Figure 3.6
- 3.6. Programme management decision making
- 3.7. Decision-making components
- 3.8. The decision-making environment of a programme
- 3.9. Decision-making models
- 3.10. Contingency view
- Flyvbjerg B (2014)
- Hanford M (2004)
- T309-04.pdf
- 4.1. Description
- Figure 4.1
- 4.2. Case study: Programme One
- 4.2.1 Narrative
- 4.2.2 Data
- 4.2.3 Management structure
- 4.2.4 Staff
- 4.2.5 Milestone dates for condominiums
- Figure 4.2
- 4.2.6 Pricing and cost control
- 4.2.7 Actual cost
- 4.2.8 What went wrong and right
- Table 4.1
- 4.2.9 The benefits of programme management application
- 4.3. Case study: Programme Two
- 4.3.1 Narrative
- Figure 4.3
- 4.3.2 Data
- 4.3.3 Structure
- Table 4.2
- Figure 4.4
- 4.3.4 Staff
- 4.3.5 Milestone dates for schools
- 4.3.6 Pricing and cost control
- 4.3.7 Actual cost
- 4.3.8 What went wrong and right
- Table 4.3
- Table 4.4
- 4.3.9 The benefits of programme management application
- 4.4. Case study: Programme Three
- 4.4.1 Narrative
- 4.4.2 Data
- 4.4.3 Structure
- 4.4.4 Staff
- 4.4.5 Milestone dates
- Figure 4.5
- Figure 4.6
- 4.4.6 Pricing and cost control
- 4.4.7 Actual cost
- 4.4.8 What went wrong and right
- Table 4.5
- 4.4.9 The benefits of programme management application
- 4.5. Case study: Programme Four.
- 4.5.1 Narrative
- 4.5.2 Data
- 4.5.3 Structure
- 4.5.4 Staff
- 4.5.5 Milestone dates for housing programme
- 4.5.6 Pricing and cost control
- 4.5.7 Actual cost
- Figure 4.7
- Figure 4.8
- Figure 4.9
- Table 4.6
- 4.5.8 What went wrong and right
- 4.5.9 The benefits of programme management application
- 4.6. Summary
- 4.6.1 What went wrong and right
- 4.6.2 The benefits of programme management application
- Reference
- Flyvbjerg B (2006)
- T309-05.pdf
- 5.1. Introduction
- 5.2. The contract between a client and a programme management consultancy practice
- 5.3. Procurement routes
- 5.3.1 The traditional approach
- 5.3.2 Design and build
- Figure 5.1
- Figure 5.2
- 5.3.3 Design, build and operate (DBO)
- 5.3.4 Design, build, operate and transfer (DBOT)
- 5.3.5 Design, build, operate and maintain (DBOM)
- 5.3.6 Single purpose entities (SPE)
- 5.3.7 Joint ventures (JV)
- 5.3.8 Consortia
- 5.3.9 Partnering
- Figure 5.3
- 5.3.10 Collaboration
- 5.3.11 Programme alliancing
- 5.4. A building information modelling (BIM) approach to contracts
- 5.5. Main elements of a programme management contract
- FIDIC (1999a)
- FIDIC (1999b)
- JCT (2011a)
- JCT (2011b)
- T309-06.pdf
- 6.1. Network-based scheduling - an introduction
- 6.2. Project planning - a critical path method
- Figure 6.1
- Figure 6.2
- 6.3. Programme planning
- Figure 6.3
- 6.3.1 Activities in a programme
- Figure 6.4
- 6.3.2 Planning and scheduling a programme
- 6.4. Critical path method: an analytical review
- 6.5. Impact of the critical path method on liquidated damages
- 6.6. Extension of time
- 6.7. Planning complexity and float
- 6.8. Acceleration of a programme
- Figure 6.5
- 6.9. Risk distribution in managing delays
- Figure 6.6
- 6.10. Completion, early completion and acceleration
- 6.11. Programme float ownership.
- 6.12. Programme structure within a programme
- 6.13. Responsibilities and function within a structure
- Cooke B and Williams P (2009)
- Haugan T (2002)
- Lester A (2007)
- Levy S (2012)
- Lewis J (2011)
- Nieminen A and Lehtonen M (2008)
- Payne JH and Turner JR (1999)
- T309-07.pdf
- 7.1. Design definition
- 7.1.1 Programme management definition for design
- 7.1.2 Good design principles
- Figure 7.1
- 7.1.3 Integrated design approach
- Figure 7.2
- 7.1.4 Good design - paradox
- Figure 7.3
- 7.2. Design roles and responsibilities
- 7.2.1 Traditional UK design roles
- 7.2.2 Traditional US professional roles and responsibilities
- 7.2.3 Supporting discipline roles
- 7.2.4 Charter agreements
- 7.3. Design work stages
- 7.3.1 Seven broad stages of the design process
- 7.3.2 Design stages by professional international design entities
- Figure 7.4
- 7.3.3 Royal Institute of British Architects (RIBA) work stages
- 7.3.4 American Institute of Architects (AIA) work stages
- 7.3.5 Simplified design work stages
- 7.4. Design tools for programme management
- 7.4.1 Parametric and algorithmic techniques for design in programme management
- 7.4.2 Parametric design
- 7.4.3 Algorithmic design
- 7.4.4 Building information modelling management (BIMM)
- 7.5. Urban programme management
- 7.5.1 Charter cities
- 7.5.2 Destination and place branding
- 7.6. Case studies in programme management
- 7.6.1 Case study 1: BBC programming for the 2012 London Olympics
- 7.6.2 Case study 2: Olympic design, venue and infrastructure delivery
- American Institute of Architects (AIA) (2014)
- BBC (2014)
- T309-08.pdf
- 8.1. Programme management trends
- 8.1.1 International trends
- 8.1.2 National trends
- 8.1.3 Regional trends
- 8.1.4 Local trends.
- 8.2. Future challenges, tools, and new techniques for design in programme management
- 8.2.1 Parametric design trends
- 8.2.2 Algorithmic design trends
- 8.2.3 Building information modelling management (BIMM) trends
- 8.3. Future trends in programme management
- 8.3.1 Future city programmes
- 8.3.2 Resource programmes
- 8.3.3 The changing programme paradigm
- 8.4. Trends that dictate the need for change in programme management procedures
- 8.5. Possible improvements in programme management in the™future
- 8.6. Conclusion
- Pajín L (2014)
- T309-09ind.pdf.
- Notes:
- Includes bibliographical references and index.
- Description based on online resource; title from home page (viewed on December 9, 2015).
- ISBN:
- 1-5231-0555-0
- 0-7277-6015-7
- OCLC:
- 954545846
The Penn Libraries is committed to describing library materials using current, accurate, and responsible language. If you discover outdated or inaccurate language, please fill out this feedback form to report it and suggest alternative language.