My Account Log in

1 option

Programme management in construction / Peter T. Barnes, Roy Farren, Ali D. Haidar and Kenneth P. Wells.

Knovel Civil Engineering & Construction Materials Academic Available online

View online
Format:
Book
Author/Creator:
Barnes, Peter, 1954- author.
Farren, Roy, author.
Haidar, Ali D., author.
Wells, Kenneth P., author.
Language:
English
Subjects (All):
Project management.
Construction industry--Management.
Construction industry.
Physical Description:
1 online resource (156 pages)
Place of Publication:
London : ICE Publishing, 2015.
Summary:
'Programme Management in Construction' provides a comprehensive introduction to the application of programme management in the construction industry, demonstrating detailed coverage of programme management techniques through best practice guidance and case study examples.
Contents:
T309-00.pdf
T309-01.pdf
1.1. An overview
1.2. Programme management definitions
Figure 1.1
Figure 1.2
1.3. Programme phases
Figure 1.3
Figure 1.4
1.3.1 Pre-construction
1.3.2 Construction
1.3.3 Post-construction
1.3.4 Facility management
1.4. The role of the programme manager
Figure 1.5
Figure 1.6
Figure 1.7
References
Brown JT (2008)
Martinsuo M and Lehtonen P (2006)
Project Management Institute (2008)
Ritz G and Levy S (2013)
Tobis I and Tobis M (2002)
T309-02.pdf
2.1. Programme process
Figure 2.1
Figure 2.2
2.2. Programme requirements
Figure 2.3
2.3. Scope management
2.4. Cost management
Figure 2.4
Figure 2.5
2.5. Schedule management
2.6. Programme delivery methods
2.7. Programme management plan
2.8. Design stage management of a programme
2.9. Delivering and measuring programme quality
2.10. Programme cost stage management
2.11. Building information modelling (BIM)
2.12. Quality control
2.13. Programme commissioning
2.14. Programme management report
2.15. Programme management quality assurance
2.16. Programme management consultancies' scope of services - a™case study
2.16.1 Case study (consultant's role)
2.16.2 Organisation strengths and resources
2.16.3 Preparation of detailed design and tender documents
Figure 2.6
2.16.4 Programme supervision
Figure 2.7
Figure 2.8
2.16.5 Contractual issues
2.16.6 Quality control and quality control services
Table 2.1
2.17. Design and design activities
2.18. Programme pre-construction documents
Figure 2.9
2.19. Programme execution
2.19.1 Human resources
2.19.2 Supervision and engineering
2.19.3 Technical support
2.20. Programme management compared to portfolio management
2.21. Summary: objectives of programme management.
Figure 2.10
Dietrich, PH and Lehtonen, P (2005)
Eweje J, Turner R and Müller R (2012)
Pellegrinelli S (2008)
Reiss G and Rayner P (2012)
Teller J et al. (2012)
T309-03.pdf
3.1. Pre-planning framework in programme management
3.2. Pre-goal-setting
Figure 3.1
3.3. Execution modelling
Figure 3.2
Figure 3.3
3.4. Decision makers' hierarchy in a programme
Figure 3.4
Figure 3.5
3.4.1 Programme management team responsibilities during pre-planning
3.5. Decision-making framework
Figure 3.6
3.6. Programme management decision making
3.7. Decision-making components
3.8. The decision-making environment of a programme
3.9. Decision-making models
3.10. Contingency view
Flyvbjerg B (2014)
Hanford M (2004)
T309-04.pdf
4.1. Description
Figure 4.1
4.2. Case study: Programme One
4.2.1 Narrative
4.2.2 Data
4.2.3 Management structure
4.2.4 Staff
4.2.5 Milestone dates for condominiums
Figure 4.2
4.2.6 Pricing and cost control
4.2.7 Actual cost
4.2.8 What went wrong and right
Table 4.1
4.2.9 The benefits of programme management application
4.3. Case study: Programme Two
4.3.1 Narrative
Figure 4.3
4.3.2 Data
4.3.3 Structure
Table 4.2
Figure 4.4
4.3.4 Staff
4.3.5 Milestone dates for schools
4.3.6 Pricing and cost control
4.3.7 Actual cost
4.3.8 What went wrong and right
Table 4.3
Table 4.4
4.3.9 The benefits of programme management application
4.4. Case study: Programme Three
4.4.1 Narrative
4.4.2 Data
4.4.3 Structure
4.4.4 Staff
4.4.5 Milestone dates
Figure 4.5
Figure 4.6
4.4.6 Pricing and cost control
4.4.7 Actual cost
4.4.8 What went wrong and right
Table 4.5
4.4.9 The benefits of programme management application
4.5. Case study: Programme Four.
4.5.1 Narrative
4.5.2 Data
4.5.3 Structure
4.5.4 Staff
4.5.5 Milestone dates for housing programme
4.5.6 Pricing and cost control
4.5.7 Actual cost
Figure 4.7
Figure 4.8
Figure 4.9
Table 4.6
4.5.8 What went wrong and right
4.5.9 The benefits of programme management application
4.6. Summary
4.6.1 What went wrong and right
4.6.2 The benefits of programme management application
Reference
Flyvbjerg B (2006)
T309-05.pdf
5.1. Introduction
5.2. The contract between a client and a programme management consultancy practice
5.3. Procurement routes
5.3.1 The traditional approach
5.3.2 Design and build
Figure 5.1
Figure 5.2
5.3.3 Design, build and operate (DBO)
5.3.4 Design, build, operate and transfer (DBOT)
5.3.5 Design, build, operate and maintain (DBOM)
5.3.6 Single purpose entities (SPE)
5.3.7 Joint ventures (JV)
5.3.8 Consortia
5.3.9 Partnering
Figure 5.3
5.3.10 Collaboration
5.3.11 Programme alliancing
5.4. A building information modelling (BIM) approach to contracts
5.5. Main elements of a programme management contract
FIDIC (1999a)
FIDIC (1999b)
JCT (2011a)
JCT (2011b)
T309-06.pdf
6.1. Network-based scheduling - an introduction
6.2. Project planning - a critical path method
Figure 6.1
Figure 6.2
6.3. Programme planning
Figure 6.3
6.3.1 Activities in a programme
Figure 6.4
6.3.2 Planning and scheduling a programme
6.4. Critical path method: an analytical review
6.5. Impact of the critical path method on liquidated damages
6.6. Extension of time
6.7. Planning complexity and float
6.8. Acceleration of a programme
Figure 6.5
6.9. Risk distribution in managing delays
Figure 6.6
6.10. Completion, early completion and acceleration
6.11. Programme float ownership.
6.12. Programme structure within a programme
6.13. Responsibilities and function within a structure
Cooke B and Williams P (2009)
Haugan T (2002)
Lester A (2007)
Levy S (2012)
Lewis J (2011)
Nieminen A and Lehtonen M (2008)
Payne JH and Turner JR (1999)
T309-07.pdf
7.1. Design definition
7.1.1 Programme management definition for design
7.1.2 Good design principles
Figure 7.1
7.1.3 Integrated design approach
Figure 7.2
7.1.4 Good design - paradox
Figure 7.3
7.2. Design roles and responsibilities
7.2.1 Traditional UK design roles
7.2.2 Traditional US professional roles and responsibilities
7.2.3 Supporting discipline roles
7.2.4 Charter agreements
7.3. Design work stages
7.3.1 Seven broad stages of the design process
7.3.2 Design stages by professional international design entities
Figure 7.4
7.3.3 Royal Institute of British Architects (RIBA) work stages
7.3.4 American Institute of Architects (AIA) work stages
7.3.5 Simplified design work stages
7.4. Design tools for programme management
7.4.1 Parametric and algorithmic techniques for design in programme management
7.4.2 Parametric design
7.4.3 Algorithmic design
7.4.4 Building information modelling management (BIMM)
7.5. Urban programme management
7.5.1 Charter cities
7.5.2 Destination and place branding
7.6. Case studies in programme management
7.6.1 Case study 1: BBC programming for the 2012 London Olympics
7.6.2 Case study 2: Olympic design, venue and infrastructure delivery
American Institute of Architects (AIA) (2014)
BBC (2014)
T309-08.pdf
8.1. Programme management trends
8.1.1 International trends
8.1.2 National trends
8.1.3 Regional trends
8.1.4 Local trends.
8.2. Future challenges, tools, and new techniques for design in programme management
8.2.1 Parametric design trends
8.2.2 Algorithmic design trends
8.2.3 Building information modelling management (BIMM) trends
8.3. Future trends in programme management
8.3.1 Future city programmes
8.3.2 Resource programmes
8.3.3 The changing programme paradigm
8.4. Trends that dictate the need for change in programme management procedures
8.5. Possible improvements in programme management in the™future
8.6. Conclusion
Pajín L (2014)
T309-09ind.pdf.
Notes:
Includes bibliographical references and index.
Description based on online resource; title from home page (viewed on December 9, 2015).
ISBN:
1-5231-0555-0
0-7277-6015-7
OCLC:
954545846

The Penn Libraries is committed to describing library materials using current, accurate, and responsible language. If you discover outdated or inaccurate language, please fill out this feedback form to report it and suggest alternative language.

Find

Home Release notes

My Account

Shelf Request an item Bookmarks Fines and fees Settings

Guides

Using the Find catalog Using Articles+ Using your account